week 1

Week 1 - hole dug, base poured
Week 2 - foundation forms installed, foundation poured and forms removed, well connected (pump installed), main floor joists delivered
Week 3 - tbd...

week 2
In the garden - the end of August has been quite spectacular, both weather wise, house building wise and garden wise.  (OK, a little rain would help the garden a lot, but for building it's been perfect.)  The daylilies are ending - just a few of the double orange left to bloom; the Echinacea are past their prime; Rudbeckia is in all its glory.  Seriously.  My whole yard is awash in or

week 2


compost bin on left finally emptied and screened
ange and yellow from Rudbeckia and the beginning of Goldenrod.

Bonus - I sorted out my third compost bin - emptying about eight years of accumulation to find some nice compost down in there!